The sunny days of autumn fully reflect our enthusiasm for Vox Vertical Village. We took advantage of the last weeks of sunny weather to complete the excavations and start working on the foundation of the building.

1/6

We have already poured the equalizing concrete which gives us a solid foundation for fixing foundation pillars. We also mounted some of the horizontal waterproofing underneath the foundation and we succeeded in building the foundations of the two cranes to be installed in the near future. At the moment, we also started the assembly works for the foundation reinforcement.

We’re glad to see things taking shape and we feel lucky to have such a great and enthusiastic team. For up-to-date status information, we invite you to follow our Facebook page.

Thank you for your interest in Vox Vertical Village. We’d be happy to contact you at that point, if you’d like to register your interest.